SGMC Generator Plant

Completed June 2013 · 18-month build · Valdosta Electric as prime contractor

Valdosta Electric served as prime contractor on the complete replacement of the original 1950s generator plant (last upgraded in the 1980s) — now one of the most sophisticated plants of its kind. Two 2 MW Caterpillar gensets with provisions for a third; four 4000 A 277/480 V 3-phase services; new normal and emergency power infrastructure for the entire facility; 14 miles of conduit in underground duct banks and over 45 miles of cabling installed. Sixty-seven major cutovers totaling 530 man-hours were completed with only 12 minutes of total outage time to the facility.