SGMC Berrien ED
Completed 2025 · 26,550 sq ft · two stories · General Contractor: Cauthan Construction Company · Architect: McCall Architecture
SGMC Health's new Berrien Emergency Department addition rises as a striking architectural landmark on the hospital campus — a two-story, 26,550-square-foot expansion featuring a distinctive metal panel exterior designed by McCall Architecture. Completed in 2025, this facility addresses critical space needs and positions the hospital for continued growth.
Floor-by-Floor Program
The first floor, spanning 12,800 square feet, features a new covered emergency department entrance with a welcoming lobby, a dedicated ambulance bay that flows directly into the trauma and resuscitation room, and 8 exam rooms. All exam rooms are equipped with prefabricated headwalls, including 2 bariatric isolation rooms and 2 psychiatric exam rooms. A central nurses station overlooks the floor, providing coordinated care oversight.
The second floor, encompassing 13,750 square feet, addresses a critical operational gap. Much of this space is dedicated to much-needed storage and administrative offices for both the new addition and the existing hospital, accommodating the facility's significant growth in recent years. Two elevators connect both floors, ensuring seamless patient and staff mobility.
Power Infrastructure & Electrical Systems
A utility radial feed provides the primary power source, backed by a 600 kW CAT diesel generator. The system features three independent Automatic Transfer Switches (ATS) serving equipment circuits, critical circuits, and life-safety circuits respectively — a redundant configuration that guarantees emergency department operations continue uninterrupted during any power event.
Coordination & Execution
Valdosta Electric partnered with general contractor Cauthan Construction Company and McCall Architecture to bring this modern emergency facility to life.
.png)