Prinsco
Oct 2023 – Aug 2024 · 64,000 sq ft · General Contractor: Gideon Constructors
Valdosta Electric partnered with general contractor Gideon Constructors on Prinsco's new 64,000-square-foot corrugated pipe manufacturing facility in Valdosta, running from October 2023 to August 2024.
Power Infrastructure
Valdosta Electric installed all electrical components from the secondary side of the utility transformer, feeding two 2,500 A switchboards. These switchboards power all of the facility's major equipment: four production lines, a bridge crane, coolers, silos, and a 2,000-square-foot front office — with room built in for an additional production line in the future.